Provides the exact cumulative time or cost required for units m through n (inclusive) using the Crawford unit model
unit_cum_exact(t, n, r, m = 1, na.rm = FALSE)
NA
values be removed?library(learningCurve) # An estimator believes that the first unit of a product will # require 100 labor hours. How many total hours will be required # for 125 units given the organization has historically experienced # an 85% learning curve? unit_cum_exact(t = 100, n = 125, r = .85)#> [1] 5201.085## [1] 5201.085