Provides the exact cumulative time or cost required for units m through n (inclusive) using the Crawford unit model

unit_cum_exact(t, n, r, m = 1, na.rm = FALSE)

Arguments

t
time (or cost) required for the mth unit of production
n
The unit you wish to predict the cumulative time (or cost) to
r
learning curve rate
m
mth unit of production (default set to 1st production unit)
na.rm
Should NA values be removed?

Examples

library(learningCurve) # An estimator believes that the first unit of a product will # require 100 labor hours. How many total hours will be required # for 125 units given the organization has historically experienced # an 85% learning curve? unit_cum_exact(t = 100, n = 125, r = .85)
#> [1] 5201.085
## [1] 5201.085